Stay in your lane! Wherever that is: Montreal road painting is behind schedule
The lines marking the lanes on the busy de la Verendrye Blvd. near Highway 15 are barely visible.
It is one of many of Montreal's roads lacking paint at the moment, as city contractors try desperately to fill paint orders that have been delayed.
Charles Paquette, a contractor from Scelltech Inc., said a supply-chain issue starting in Texas caused a significant delay in deliveries.
"There was a major storm that hit Texas a couple of months ago that impacted all production for safety painting for the line painting in the cities," he said.
He said COVID-19 also played a role in the delay.
A spokesperson for the City of Montreal said priority painting was completed July 11, and that it remains on schedule for axial marking "with the exception of areas under construction and areas with upcoming projects."
CTVNews.ca Top Stories
Grandparent scam: London, Ont., senior beats fraudsters not once, but twice
It was a typical Tuesday for Mabel Beharrell, 84, until she got the call that would turn her world upside down. Her teenaged grandson was in trouble and needed her help.
Deaths of 4 people on Sask. farm confirmed as murder-suicide
The deaths of four people on a farm near the Saskatchewan village of Neudorf have been confirmed a murder-suicide.
George Washington family secrets revealed by DNA from unmarked 19th century graves
Genetic analysis has shed light on a long-standing mystery surrounding the fates of U.S. President George Washington's younger brother Samuel and his kin.
Bus plunges off a bridge in South Africa, killing 45 people. An 8-year-old child is only survivor
A bus carrying worshippers headed to an Easter festival plunged off a bridge on a mountain pass and burst into flames in South Africa on Thursday, killing at least 45 people, authorities said.
Why some Christians are angry about Trump's 'God Bless the USA' Bible
Former U.S. President Donald Trump is officially selling a copy of the Bible themed to Lee Greenwood’s famous song, 'God Bless the USA.' But the concept of a Bible covered in the American flag has raised concern among religious circles.
Sunshine list: These were the Ontario public sector's highest earners in 2023
Ontario released its annual sunshine list Thursday afternoon, noting that the largest year-over-year increases were in hospitals, municipalities, and post-secondary sectors.
Calgary bridges remain closed due to ongoing police incident
Calgary police have shut down a number of bridges into and out of the downtown core as officers deal with a distraught individual.
Kinew, Poilievre meet at Manitoba legislature, discuss each other's priorities
Premier Wab Kinew and federal Conservative Leader Pierre Poilievre met at the Manitoba legislature Thursday afternoon.
Rainfall warnings of up to 80 mm among weather alerts in effect for 6 provinces
Rainfall warnings of up to 90 millimetres and other alerts have been issued for six Canadian provinces, according to the latest forecasts.