Hydro-Québec to expand its transmission lines
Quebecers can expect to see a forest of new transmission lines over the next few years.
On Monday, Hydro-Québec announced the launch of the first phase of development and reinforcement work on its power transmission network – the high-voltage lines that carry large quantities of electricity from where it is generated to the substations that redistribute it to clients.
It was already known that Hydro-Québec's wants to massively increase its electricity production, but once produced, this electricity must be transported.
Between now and 2035, the utilities corporation plans to invest a total of $50 billion to install some 5,000 kilometers of transmission lines, about half at high voltage (735 kilovolts and 315 kilovolts) and the other half at intermediate voltage (between 69 kV and 315 kV) for regional development and local loads.
1600 new towers
The first phase announced on Monday represents investments of around $10 billion to reinforce the existing network, build almost 850 kilometers of new 735 kV or 315 kV transmission lines, and add five new substations.
The company's plan already includes the installation of 1,600 new towers for this first phase.
This phase will be carried out along three axes: one on the North Shore in the corridor between Sept-Îles and Baie-Comeau, the second in the Appalachian-Lower St. Lawrence sector covering the Beauce to the area bordering the New Brunswick border near Edmundston, and the third in the St. Lawrence Valley, inland on the North Shore from the Capitale-Nationale region through the Mauricie region to the Lanaudière region.
Hydro's Executive Vice President and Chief Infrastructure Officer, Claudine Bouchard, promised that the work, which is expected to generate $7 billion in spinoffs, will benefit the regions where it takes place.
“You've seen that we have two major development axis projects in the regions of Quebec, so we're going to make sure we generate regional economic spinoffs in those regions and hire the workforce to be able to develop the lines,” she said.
The precise locations where these lines will be installed have yet to be determined, but Hydro-Québec makes no secret of its preference for installations in existing corridors. “Of course, not opening a new corridor is always the least-impact route, but at the same time, we have to take into account community concerns. That's why we're currently in preliminary consultations to hear these kinds of elements from our partners in the various regions concerned by the three axes of the transportation project,” said Bouchard.
While such corridors already exist in the Côte-Nord and Vallée du Saint-Laurent corridors, this is not the case in the Appalaches-Bas-Saint-Laurent corridor.
Social acceptability
In presenting this first phase on Monday, Bouchard emphasized social acceptability and stressed the consultations to be held with the 25 regional county municipalities (RCMs), some 200 municipalities and a dozen aboriginal communities that will be impacted by these structures.
Hydro-Québec decided to get ahead of the game by initiating consultations before even thinking about routes, an unprecedented approach for the state-owned company.
“This is the first time we've met with representatives of non-Indigenous and Indigenous communities to discuss their concerns and their plans to develop their territory as part of our project definition. Then we'll go out and talk to the public to find the route with the least impact,” said Bouchard.
All three corridors aim to improve system reliability and resistance to increasingly frequent extreme weather events. On the North Shore, the more focused objective is to enable the development of new renewable energy sources and support industrial development; on the Appalachian-Lower St. Lawrence axis, the state-owned company wants to support the development of wind power potential in eastern Quebec, while development of the St. Lawrence Valley axis will enable the transmission of additional energy from northern and eastern Quebec, increase the capacity of high-voltage lines that have reached their limit, and supply the growing needs of urban centers in the south of the province.
The new infrastructures will be gradually commissioned between 2031 and 2036.
This report was first published in French by The Canadian Press Nov. 4, 2024.
CTVNews.ca Top Stories
DEVELOPING Gunman's steps after killing UnitedHealthcare's CEO gives police new clues in hunt for the killer
As the hunt for a masked gunman who stalked and killed the head of the largest U.S. health insurer moved into its third day Friday, surveillance footage provided more clues about the suspect's travels and the places he visited before the shooting.
Purolator, UPS pause shipments from couriers amid Canada Post strike
Purolator and UPS have paused shipments from some courier companies as they try to work through a deluge of deliveries brought on by the Canada Post strike.
NDP's Singh forces debate on $250 cheques for more Canadians; Conservatives cut it short
With the fate of the federal government's promised $250 cheques for 18.7 million workers hanging in the balance, the NDP forced a debate Friday on a motion pushing for the prime minister to expand eligibility. The conversation was cut short, though, by Conservative MPs' interventions.
Sask. father who kept daughter from mom to prevent COVID-19 vaccine free from additional prison time
Michael Gordon Jackson, the Saskatchewan father who withheld his then seven-year-old daughter from her mom for nearly 100 days to prevent the girl from getting a COVID-19 vaccine, was handed a 12-month prison sentence and 200 days probation on Friday, but credited with time served.
Ticketmaster hidden fees settlement credits expected in 2025 following class-action lawsuit by Regina lawyer
A longstanding lawsuit against Ticketmaster is nearing its end, with a judge expected to approve the more than $6 million dollar settlement before the end of the year.
What is still being delivered? What to know about the Canada Post strike
With Canada Post workers on strike, many individuals and businesses are facing the challenge of sending and receiving mail. Here are the answers to some of Canadians’ most-asked questions.
How the combination of diapers and splash pads led to 10K illnesses
New research is raising concerns about the safety of splash pads, which can be ground zero for germs and greatly increase the risk of spreading disease.
Which guns are now banned in Canada? Here's what you need to know
Canada is expanding its federal ban on firearms, adding 324 makes and models of guns to the prohibited weapons list, effective immediately.
Canada's 6.8% jobless rate boosts bets for 50-point interest rate cut
Canada had 1.5 million unemployed people in November, propelling its jobless rate to a near-eight-year high outside of the pandemic era and boosting chances of a large interest rate cut on Dec. 11.