Even though the race is over-- local traffic doesn't get the green light just yet.

The City of Montreal is urging drivers to maintain a little bit of patience while workers dismantle the Formula E circuit. Most of the work will be done during the night, and is expected to stretch on until August 9th. 

Beginning Monday morning, the following routes will be re-opened to traffic:

  • Viger East between Papineau and Berri
  • Saint-Antoine East between Berri and Notre-Dame East.
  • St. Hubert between Viger East and Saint-Antoine East
  • Papineau (Northbound) between Viger East and Boul. Rene Levesque. 

The following routes within the paramaters of the Formula E circuit will also gradually reopen throughout Monday morning:

  • Amherst St. between de Maisonneuve and Viger East
  • De la Gauchetiere East between Wolfe and Saint-Denis
  • All of the transverse streets between Rene-Levesque East and Vger East, from Saint-Hubert to Wolfe St.